Water treatment plant, Eindhoven, Netherlands

  • Statinio tipas:
  • Pramoniniai pastatai
  • Infrastruktūra
Per visą ekraną Užverti Street View

For the raising of the sedimentation basin within the sewage treatment plant in Eindhoven, the precast elements are connected to each other in a fast and efficient way with the Peikko SUMO® wall shoe connection. 

This dry connection consists of a SUMO® Wall shoe cast in one element and an HPM® anchor bolt cast in the other element. Together this forms the wall shoe joint that absorbs tensile loads. To provide protection against corrosion, the connections are galvanized in this project.

Projekto duomenys

Vystytojas:
Waterschap De Dommel
Rangovas:
Van Boekel Bouw & Infra
Surenkamojo g/b gamintojas:
Haitsma Beton
Projektavimo darbų pradžia:
2019
Užbaigimo metai:
2020

Panaudoti mūsų sprendimai