In the summer of 2023, Peikko supplied key foundation components to the Asterholma project in Åland, including one Rock Adapter foundation fully manufactured in Finland.

SUVIC managed the civil works, with Peikko providing 40 pieces of FATBAR® 56 Post-Tensioned Anchors, each 12 meters long, along with one Rock Adapter plate set with short tower bolts for an Enercon E70 turbine.

The Rock Adapter solution features the most compact foundation, reducing concrete use by eliminating the traditional anchor cage.

The FATBAR® Post-Tensioned Anchor offers proven quality as an ETA-assessed and CE-marked product, ensuring a safe and reliable solution. Its compact design is optimized for material efficiency, environmental consciousness, and cost-effective installation. Additionally, the FATBAR anchor simplifies risk management with easy re-tensioning, supporting hassle-free maintenance throughout the foundation's lifecycle.

For more information on FATBAR®, please visit: Peikko.com/fatbar

 

Plačiau down-arrow.png

Projekto duomenys

Vystytojas:
Asterholma Vindenergi AB
Rangovas:
Suvic Oy
Projektavimo darbų pradžia:
2023
Užbaigimo metai:
2023
Jėgainių kiekis:
1
Jėgainės gamintojas:
Enercon
Jėgainės galia, MW:
E-70 E4/S/69/4F/01 2.8MW
Aukštis, m:
69